Business
Risk

CGL, Builders Risk Coverage and Exclusions When Construction Defects Cause Property Damage

When physical damage to property is caused by defects or defective work, do CGL and Builders Risk policies cover the damage? It depends…
By Jeffrey Cavignac
April 23, 2021
Topics
Business
Risk

Direct damage to property under construction caused by faulty or defective work or defective materials has been a coverage issue for decades. Two specific policies, the Commercial General Liability for the contractors building the structure and the Builders Risk Policy on the project both are sources of potential coverage.

A CGL policy protects the named insured (the contractor in this case) from third party liability arising out of the insured’s operations that results in either bodily injury or property damage. Damage to property caused by poor workmanship or defective materials would qualify as property damage. To understand how the CGL policy might respond to claims such as these, it is necessary to evaluate several exclusions in the CGL policy.

CGL policies cover “property damage,” defined as physical injury to tangible property, including loss of use of such property, and loss of use of tangible property that has not been physically injured.

Exclusion M provides that there is no coverage for loss of use of property that has not been physically injured due to a defect in the work. This is significant, because it means that there is no CGL coverage for defective work without physical injury to the work.

For example, prior to completion on a construction project, inspection revealed that windows were not properly installed, making them prone to leaks. But no leaking had occurred. Removing and reinstalling the windows delayed the project by two weeks. The owner made a claim against the GC for lost revenue for the two weeks. There is no CGL coverage because the loss of use was purely due to defective work, with no physical injury (the CGL only covers liability that results in bodily injury or tangible property damage).

There are two additional exclusions applicable to property damage in the course of construction, exclusions J.5 and J.6:

  • Exclusion J.5 excludes property damage to that particular part of property on which the insured or its contractors are working if the property damage arises out of their work. This exclusion typically applies where a mistake in performance causes damage. Resultant property damage caused by the mistake would be covered, but damage to “that particular part” that caused the loss would not be covered. For example, an electrical contractor caused a fire while working in the mechanical room that triggered the fire suppression system building-wide, causing widespread water damage. The exclusion applies only to the electrical components in the mechanical room damaged by fire.
  • Exclusion J.6 excludes property damage to that particular part of property that must be repaired or replaced because the insured’s work was defectively performed on it. For example, a concrete subcontractor improperly mixed a concrete batch, resulting in a section of foundation that cracked, causing a shift in the structure. Structural components supported by the faulty area were damaged. The section needed to be demolished and re-poured with major repairs needed to the rest of the structure. The re-pour is excluded but the damage to the rest of the structure was not.
    Сonfidence in the future

In both cases, the CGL affords coverage for physical damage to the work caused by defects or defective work--basically the ensuing damage. In neither case would the General Liability policy cover that particular part that was either worked on or needed to be repaired or replaced due to defective work.

Project-Specific CGL Coverage (OCIPs and CCIPs) needs to be considered in a different light. Nearly every OCIP or CCIP will include an exclusion for property damage to the insured project during the course of construction (note, that a small minority of insurers may remove this exclusion if the contractor can provide evidence of a LEG 2 or 3 endorsement). These are often referred to as “Course of Construction” or “Builder’s Risk Exclusions.” These exclusions are added with the expectation that the builder’s risk insurance should provide coverage for damage to the structure during the course of construction.

Providing coverage under a first party property form is preferred to a third- party liability form because it should eliminate any litigation. The key is negotiating broad and favorable terms under the Builders Risk policy. A well-written Builders Risk policy will include:

  • all stakeholders as insureds;
  • comply with the contractual terms of the contract;
  • possibly include earthquake and flood;
  • include water related damage other than flood; and
  • ideally include not only resultant damage caused by defective work or materials but if available damage to that “particular part” that caused the problem.

The U.S. builder’s risk market is dominated by manuscript forms. There are some consistencies, but each form must be carefully reviewed. With respect to coverage for property damage during the course of construction caused by defective work, domestic forms generally fall into two categories.

The first type, which is less common, excludes all damage caused by, or arising out of faulty workmanship. This removes coverage for repairing defective work as well as for any damage to the project resulting from the defective work. These forms offer less coverage than the ISO CGL policy and should be avoided.

The second, more common, domestic form excludes loss or damage caused by faulty work, unless the damage is caused by a covered cause of loss. These are commonly referred to as “ensuing loss exceptions.” Taking the example of the concrete subcontractor who improperly mixed the concrete that resulted in structural damage, in this case the re-pour is excluded but the damage to the rest of the structure is not because collapse is a covered peril.

Most domestic builder’s risk policies with ensuring loss exceptions provide roughly the same scope of coverage for property damage during the course of construction as an ISO CGL policy. Neither policy provides coverage for the cost of replacing defective work, but both policies cover direct damage to the rest of the project caused by the defective work. In the case of a Builders Risk policy this ensuing loss must be caused by a covered peril.

An underwriting syndicate in London came up with proposed endorsements that specifically address the faulty workmanship issue. Authored by the London Engineering Group, these have come to be known as LEG1, LEG2 and LEG3:

  • LEG1 is the most restrictive. It excludes coverage for all loss or damage “due to defects of material workmanship, design plan or specification,” whether damage to other property has occurred or not. LEG1 is the basic equivalent of the first category of US market forms that exclude all damage caused by defective work, without the “ensuing loss exception.”
  • LEG2 excludes coverage for all loss or damage “due to defects of material workmanship, design plan or specification,” but maintains coverage for insured property damaged by the defect, except for the cost that would have been incurred if the replacement or rectification had been done before the damage. LEG2 is roughly equivalent to the U.S. market form with the “ensuing loss exception.” It covers resulting property damage to the project, but not damage to the part causing the problem. This makes LEG2 also roughly equivalent to an ISO CGL policy in terms of the scope of coverage for property damage during the course of construction.
  • LEG3 provides the broadest coverage. This endorsement extends coverage to not only the ensuing damage, but damage to that “particular part” that caused the damage. Coverage does not extend to costs “incurred to improve the original material workmanship, design plan or specification.” As long as there is resulting property damage, the LEG3 form covers all repair costs, including the cost of repairing or replacing the defective work.

LEG2 and LEG3 each contain an additional provision stating that “it is understood and agreed” that insured property shall not be considered damaged “notes solely by virtue of the existence of any defect of material workmanship, etc...”. In other words, there must be a covered cause of loss to trigger coverage. In simple terms, LEG3 coverage excludes the cost to repair a defect where there is no resulting damage, and the cost of improvements over and above the original work.

Here, in the example of the concrete subcontractor who improperly mixed the concrete that resulted in structural damage, the re-pour is covered along with damage to the rest of the structure. If, as an added safety precaution, the foundation was reinforced with metal rods, the cost of adding the metal rods would not be covered. The LEG3 form provides broader coverage for damage caused by defective work than the ISO CGL policy. The ISO CGL policy does not cover the cost of repairing or replacing defective work whereas LEG3 does. It should also be pointed out that LEG3 Endorsements are usually not available on smaller projects or frame construction.

Insuring construction projects are complex. There are numerous stakeholders as well as significant exposures, General Liability, property under construction, pollution, workers compensation, professional liability, etc.

Here are a few things to keep in mind:

  • It is always better to have a loss covered by a property policy than a liability policy to avoid the litigation costs, ill will and time litigation can take.
  • Negotiate the most favorable Builders Risk terms available. All Builders Risk policies are different and all are negotiable.
  • Understand how construction defects caused by faulty workmanship or defective products will be treated. Whenever possible a LEG3 type endorsement should be sought.
  • Communicate the coverage provided, or lack thereof to the named insureds. Just because the broker knows it, doesn’t mean the insured knows it.

There is no substitute for taking the time to understand the risks of a project and negotiating favorable terms for all stakeholders. A well written and coordinated insurance program is a critical piece to a successful project.

by Jeffrey Cavignac

Related stories

Business
How Performance-Driven Construction Management Will Improve Productivity
By Aviv Leibovici
Combining technology, people and a proactive approach to project management can lead businesses not only to success but into the future of the construction industry.
Business
'Taylor Swift Is an Economic Phenomenon': CE's Q1 2024 Economic Update and Forecast
By Grace Calengor
In our latest construction forecast webinar, ABC Chief Economist Anirban Basu offered a newly optimistic analysis of the economy—including the role that a certain pop superstar's concert tour has played in staving off recession.
Business
Keep Going: A Plan for Ensuring Business Continuity
By Christopher Durso
Business continuity is about keeping the lights on today, tomorrow and 20 years from now. A risk-control expert tells CE how companies of all sizes can start planning for it.

Follow us




Subscribe to Our Newsletter

Stay in the know with the latest industry news, technology and our weekly features. Get early access to any CE events and webinars.